§ 23-36. Piling or removal of excavated materials.  


Latest version.
  • All materials excavated from trenches and piled adjacent to the trench or in any street shall be piled, and maintained so as not to endanger those working in the trench and users of the street-and so that as little inconvenience as possible is caused to those using streets and adjoining property. Where the confines of the area being excavated are too narrow to permit the piling of excavated material beside the trench, such as might be the case in a narrow alley, the permittee shall haul the material to a storage site and then rehaul it to the trench site at the time of backfilling.

(Code 1964, § 6.70)